Phase 2 - Watermain Looping - Change Order No. 2

Information

Department:EngineeringSponsors:
Category:Change Orders

Attachments

  1. Printout

Meeting History

Nov 13, 2017 7:00 PM  Township Council Conference Meeting

Township Engineer Paul Lasek recommended that the Council approve a Change Order No. 2 to the contract for the Phase 2 Watermain Looping project which would increase the price by $30,152.36. The recommendation was approved for the adoption of the appropriate Resolution.

RESULT:APPROVED [UNANIMOUS]Next: 11/27/2017 7:00 PM
MOVER:Carlos Pomares, Councilman
SECONDER:Jenny Mundell, First Ward Councilwoman
AYES:Jenny Mundell, Nicholas Joanow, Wartyna Davis, Carlos Pomares, Michael J. Venezia
ABSENT:Carlos Bernard, Ted Gamble
Nov 27, 2017 7:00 PM  Township Council Regular Meeting
RESULT:APPROVED BY CONSENSUS